• frezik@midwest.social
    link
    fedilink
    English
    arrow-up
    2
    ·
    5 months ago

    The other side of that is matching supply to demand is basically instant. You pull power from batteries and they give you more (provided they’re not at their safe limit). There’s always a lag in getting turbines to spin up and down, and so there’s a non-trivial mismatch time.

    • Hugin@lemmy.world
      link
      fedilink
      English
      arrow-up
      2
      ·
      4 months ago

      Actually no. Batteries and thier inverter adapt in the about one second to half a second range. The massive inertia of a turbine adapts in the millisecond range.

      To maintain 60 hz you need to be in the very low milliseconds range. Remember at 60 hz you do a full sin wave cycle in 16ms.

      Turbines act as a tremendous power smoother in the grid.